A filling line can slow when it changes upstream tanks even if each tank feeds the filler at the required rate on its own. Treat the handoff as a separate trial event. Ask the plant and equipment supplier to agree which signals, time window and product conditions they will record.
Capture the window on both sides
Begin before the operator initiates the change and finish after output is steady. Record accepted packs against the same time base used for upstream events. Include any declared hold, product recovery or delayed release so paused production is visible. Run only the sequence that the plant has approved.
| Event | Measure | Result |
|---|---|---|
| Last stable output on tank A | Good packs and product batch | ___ |
| Start of tank handoff | Time and status logged by plant | ___ |
| Lowest observed filling output | Count and duration | ___ |
| First stable output on tank B | Good packs and time since start | ___ |
| Holds, stops or remaining actions | Responsible team and evidence | ___ |
Use both stable counts and the lowest window when comparing an upgraded buffer, an integration change or retained equipment.
List which upstream handoffs belong in the filling line offer
Discuss your tank handoff
Share your vessel sequence, target output and the observed gap.