A faster filler may leave the completed-pack count unchanged if the rest of the line cannot supply or clear it. Before buying capacity, collect a record of how the connected equipment behaves during an agreed production run. The comparison should make lost time and missing evidence visible.
Fix the run conditions first
Record product, container, closure, pack format and the equipment included in the test. Identify the start, finish and counting point. Keep product changes, cleaning and format changes separate from the production window used for your comparison, while recording their time elsewhere in the project assessment.
Observe machine states along the same timeline
Ask the inspection team to record when each key machine is running, waiting for upstream supply, unable to discharge or stopped by a fault. Use a common timeline. The pattern can help a specialist investigate a constraint; a queue in one photograph is not enough to diagnose the whole process.
| Observation | Question for the assessment |
|---|---|
| Waiting for containers | What interrupted upstream supply? |
| Unable to discharge | Which downstream operation or transfer stopped? |
| Fault or repeated reset | What event, duration and corrective action were recorded? |
| Operating at a reduced setting | Was the limit imposed by product, format or another machine? |
Count acceptable output at a defined point
Request acceptable-container or completed-pack counts for the same time window as the stop record. Keep rejected units visible. This separates momentary machine settings from observed process output and gives the receiving team a meaningful basis for discussing the target format.
Review transfers and accumulation with the machines
Sidel's assessment guidance includes conveyor speeds and line balance, and its accumulation guidance addresses brief stops and variations in flow. Ask which transfers and buffers are part of the sale. Their suitability for the new layout should be assessed with the container and available space in view.
Use the findings to define the purchase scope
List demonstrated constraints, uncertain observations and missing data separately. Ask for a review before pricing a faster replacement machine. The resulting brief may involve equipment, controls, format tooling or operating practices; retain the evidence that supports each proposed change.
Buying checklist
- Product and format fixed for the test
- Equipment and count point identified
- Common timeline for machine states
- Good output and rejects from the same window
- Conveyor and accumulation scope
- Named review step for each unresolved constraint